Requalification of LPG bullet tanks and upgrading of exiting plant

PROJECT DETAILS

We provide a complete set of services through various contracts from technical auditing up to construction for bullet tank revamping and site upgrade in term of piping and electrical network in order to be compliant to TOTAL standards. 

GENERAL

  • Period : 2017-2019
  • Situation : Ghannouch, Tunisia
  • Customer : Total Tunisia

SERVICES

Set of contracts for technical auditing, preliminary design, calculation notes, detailed design, procurement, factory inspection tests, shipment, tank revamping works at site, installation of supplied equipment and commissioning.

DESCRIPTION

  • Technical auditing of the existing installations and storage tanks according to TOTAL standards
  • Design and engineering of the future facilities in terms of :
    • Modification and requalification of the storage tanks
    • Upgrading of existing LPG installation
  • Conception of requalification procedures
  • Procurement and shipping of all necessary equipment
  • Supervision of local works keeping the site in operation
  • Requalification works of 3 LPG bullet tanks of 200 m³ each
  • Installation of new piping networks
  • Installation of new instrumentation, gauging system and SCADA